Problem

I need to capture and track my variations and delays costs? How do I do this in QicWorks?


Solution

There are a number of ways in which you can track how much your variations or delays are costing you within QicWorks.  
Option 1: Set up a node within your WBS Cost Structure to capture these values
Option 2: Create a specific Task within your Job to track these costs, or
Option 3: The best way! Create and use Task Categories.

Task Categories Explained

Task categories allow you to flag varying types of work and then be able to report on these easily.

You can even change the category on the fly from one to another, say a delay into a variation.

Task Categories are as the name mentions, they are captured at task level. Task levels have extraordinary flexibility and reporting capability’s

Task's allow you to:-

  1. Assign an owner
  2. Assign supervisors
  3. Assign resources
  4. Assign materials
  5. Assign order numbers
  6. Change charge rates
  7. Alter pay rules
  8. Plan and schedule
  9. Monitor progress
  10. Set priorities
  11. Set milestones
  12. Set check lists
  13. Set billing type
  14. Assign procurement and expenses items
  15. Invoice this item separately
  16. Capture time and cost
  17. Capture daily reports photos and client signatures
  18. Change status to lock or make available

Setting up Task Categories

View this help topic

Assigning a category

When adding or editing a Task you can assign a category


Reporting on a category

Actual & Billable Reports

You can easily filter content by selecting one or more category’s, remembering “Task” is the default (Being everything except for remaining categories)


Job Category Chart (Financial Area) 

Provides a quick overview of the job 



Job Category Timeline (Financial Area)

Provides a quick overview of the categories over the life of the Job




If you have any questions, get in touch with your helpful QicWorks partners




    • Related Articles

    • Task Categories

      Task categories are a great way to further filter your data. They are customisable and can be used to capture anything from variations, delays, sites, capital works, team names… the list is endless. T ask categories can be added to your Tasks on ...
    • Task

      What is a task? A Task is an activity or work package that needs to be undertaken to complete a Job. Tasks include a planned start and finish date. They are assigned resources, materials and costs to undertake. Percentage complete is reported against ...
    • Task Timer

      Task Timer The Task Timer is a great way to keep track of time on a task With only a few clicks you can create a time entry Quick View Download or send this link to your staff for training:  ...
    • Action: Create a Task

      Tasks are a great way to break down costs within a job, and can be created based on a task or job step, the shift that will preform that task, or trade. A Task can not be created on it's own.   (Task templates however can - see Task Templates for ...
    • Financial Reports